Denton County commissioners will take testimony Tuesday on special assessments for the second phase of the Green Meadows Public Improvement District, an 849-acre development district in Celina's extraterritorial jurisdiction, and then vote on bonds that those assessments would repay.
The Commissioners Court meets at 9 a.m. Dec. 1 in the third-floor courtroom of the county's Administrative Courthouse, 1 Courthouse Drive in Denton. The Green Meadows items are a public hearing on the assessment order and, later on the agenda, the bond order and a resolution approving two interlocal agreements.
What the court is being asked to do
Improvement Area #2 covers six sections, labeled K2, P2A, P2B, T1A, T1B and T1C. The amended service and assessment plan, prepared by Willdan Financial Services, lists the assessment each section would carry:
- K2, about 42 acres: $12,410,000
- P2A, about 30 acres: $7,440,000
- P2B, about 50 acres: $12,070,000
- T1A, about 30 acres: $6,126,000
- T1B, about 19 acres: $3,088,000
- T1C, about 16 acres: $4,154,000
The plan says the K2 section is expected to hold 68 lots 50 feet wide, 42 lots 60 feet wide and 30 lots 70 feet wide. Lot plans for the other sections are listed the same way in the document.
If the court adopts the assessment order, the assessments become a lien on the property. A second order would then authorize Denton County Special Assessment Revenue Bonds, Series 2026, to pay part of the cost of the streets, water, sewer and drainage work. The principal amount is left blank in the draft order.
County memos say the bonds would be paid solely from the assessments and are not backed by the county's general fund.
The bond order also approves construction, funding and acquisition agreements with three builders that would be repaid for their actual costs: K. Hovnanian Homes DFW for section K2, PH Land Holdings for P2A and P2B, and Tri Pointe Homes DFW for the three T1 sections.
Who ends up owning the work
Under the interlocal agreements, Mustang Special Utility District would take over the water and sewer lines and Smiley Road Water Control and Improvement District No. 2 would own the roads and storm drainage. County memos say the work is expected to be finished in the third quarter of 2027.